Required Attachments
Approval or Disapproval of Plans
Approval
If the reviewer determines that the PHA Plan conforms to
the three statutory standards of completeness, consistency and
compliance, the Public Housing (PH) Director, or HUD Director,
will approve the Plan. A Plan will be automatically approved
if HUD does not disapprove it within the 75-day time frame.
Troubled PHAs are exempt from the 75-day automatic approval
provision. The plan of a troubled PHA must be approved or disapproved
in writing.
The PH Director will send the PHA a letter approving the Plan.
The content of the letter may vary depending on whether the
PHA Plan also includes Capital Fund Program (CFP) or other grant
program information, whether PHAs will need to revise Capital
Fund budgets to reflect actual funding amounts, and current
grants processing procedures. If capital or other grant funds
are included, the PH Director will inform the Grant Management
Center (GMC) of PHA Plan approvals. The PH Director will also
notify the HUD web manager of the determination and the approved
plan will then be posted in the HUD web site area called "Approved
Plans."
After approval of the PHA Plan by HUD, the PHA must make its
approved Plan and the required attachments (if any) and supporting
documents related to the Plan available for review and inspection
at the principal office of the PHA during normal business hours.
PHAs are also required to promptly provide a copy of the HUD
award letter (identifying formula share allocations for the
Capital Fund Program), plan approval letter and at least one
copy of the approved plan to each Resident
Advisory Board (RAB).
Disapproval
If after reviewing a PHA Plan, the PH Director determines
that the Plan does not comply with any of the three statutory
standards, the Director will disapprove the Plan.
The PH Director may disapprove a Plan for technical or substantive
deficiencies. Technical deficiencies are those that do not have
an effect on the information that was presented to the RAB or
the public. Technical deficiencies might include, for example
mathematical errors or addition of activities in the Capital
Fund Plan that were already included in the PHAs Five-Year
Plan.
In the case of technical deficiencies, the PH Director will
disapprove the plan and specify a date for the re-submission
of the plan with the required corrections. Typically, the turn-around
time for approval of a corrected plan is approximately three
weeks and should fall within the 75-day review period. A PHA
with a Plan deemed technically deficient is not required to
consult with the Resident Advisory Board (RAB) or the public
after correcting the deficiency, and the PHA may re-submit the
Plan without the RABs assessment or a public comment/review
period.
PHA Plans that are disapproved for substantive deficiencies
require consultation with the RAB and are subject to a comment
period and a public hearing. The PH Director will specify a
reasonable time for resubmission of the plans to allow for correction
of deficiencies and the consultation process within the 75-day
review period. Substantive deficiencies are those that have
an effect on the information that was presented to the RAB or
to the public. Omitting a Capital Fund Plan is an example of
a "substantive deficiency."
HUD may determine not to release full funding under the Capital
Fund Program until the PHA Plan is approved.
Review Process Diagram

Troubled PHAS
Field Offices will conduct the review of PHA Plans of housing
authorities designated as "troubled" and those PHAs in transition
from or to a "troubled" category. The review may be conducted
Recovery Prevention Corp if applicable. The PH Director or HUD
Director will issue a written approval or disapproval letter
for these PHA Plans. PHA Plans for Troubled PHAs will not be
automatically approved if HUD does not release a document by
the end of the 75-day review period.
The Field Office may request additional documentation from
the PHA, such as Recovery Plans, to aid in making determinations
during review of a PHA Plan from a "troubled" PHA.
Moving to Work (MTW) Demonstration
PHAs under the Moving to Work
Demonstration (MTW) Program may have distinct requirements
in lieu of the PHA Plan, determined by their Moving To Work
Demonstration Agreement. PHAs operating block grants are exempt
from the requirement to submit a PHA Plan and are directed to
submit an Annual MTW Plan and an Annual MTW Report. The Annual
MTW Plan is a comprehensive framework for the PHAs activities,
including funding allocations. The Annual MTW Plan must be submitted
to HUD with a board resolution approving the plan and certifying
that a public hearing was held regarding the plan. The Annual
MTW Report includes a Consolidated Financial Report describing
the sources and uses of funds and will compare the PHAs
performance with its Annual MTW Plan. HUDs Office of Public
Housing Investments has the lead responsibility for the review
and approval of MTW Annual Plans. Field Offices have an advisory
role in the review of these plans.
MTW PHAs that do not operate block grants are not exempt from
the requirement to submit a PHA Plan and must include a separate
section describing the activities and uses of funding the PHA
is undertaking under the MTW Program. These descriptions will
be reviewed by the Field Office following the PHA Plan review
process.
Contacting Local Offices
It is recommended that a PHA contact the Field Office through
electronic mail to advise of its submission of the PHA Plan.
Field Offices should also be advised when the PHA sends the
required certifications or any other supporting document requested
by the Field Office for the review of the Plan.
A complete list of Public and Indian Housing Field Offices
is available on the HUD
PIH website.